Cruise Plan
Date: Mon, 24 Jun 1996 10:21:09 -0700 (PDT)
From: Charles Simenstad
Reply-To: Charles Simenstad
To: Ships Scripps ,
Restechs Sproul ,
Sproul RV
Cc: Denise Reed ,
Lance Horn
Mime-Version: 1.0
Tami/Louie et al.,
I left a message last week re. the ROV deployment we now definitely will
be doing July 21-26. There are two special needs: (1) a down-weight that
can be put on the Husky crane cable and used as a fixed point on the
bottom for the ROV and (2) a clean power source. The down weight, which I
originally suggested be 100-150#, Land Horn (the ROV pilot) now suggests
be 300#; can SIO dig up a somewhat hydrodynamically stable weight of that
mass that we can put on the Husky crane cable for this purpose? I seem to
remember that there is a 200# weight permanently on the Sproul, so maybe
that would just reguire an additional 100# weight? Lance says that the
ROV could handle at least 2 knots current with this sort of arrangement,
which would be great from our standpoint.
He will also need a 30 amp 110-volt dedicated power source without surges
from freezers, etc. Can we come up with that in the dry lab?.....or, not
as preferable, in the electronics van?
I'm sure there will be more information needs, but these were the most
important.
Thanks!
Si
*******************************************************************************
1996 CRETM-LMER II Cruise Schedule
July1 0800 Sproul departs SIO
2 in transit
3 "
4 "
5 "
6 1800 Sproul arrives CRE Army Corps dock
7 0800 begin onloading equipment and personnel; gearing up
8 0600 Sproul departs for Beaver Terminal, RM53;continue gearing up
1100 Sproul arrives Beaver Terminal
~1500 initiate 12-hr sampling, ebb slack 96U11;continue gearing up
9 ~0300 terminate 12-hr sampling 96U11
0800 Sproul departs for Buoy 39
1300 Sproul anchors at Buoy 39
1400 initiate 30-hr series 96S11
10 2000 terminate 30-hr series 96S11; depart for Cathlamet Bay
2200 Sproul anchors at North Channel (intertidal support)
station, Cathlamet Bay (sunset is 22:20)
11 0800 begin installation of intertidal instrumentation
12 complete installation; testing
13 ~0700 initiate intertidal flood-ebb sampling,Cathlamet Bay, 96CB1
~1900 complete intertidal flood-ebb sampling,Cathlamet Bay, 96CB1
14 ~0800 initiate intertidal flood-ebb sampling,Cathlamet Bay, 96CB2
~2000 complete intertidal flood-ebb sampling,Cathlamet Bay, 96CB2
15 ~0830 initiate intertidal flood-ebb sampling,Cathlamet Bay, 96CB3
~2030 complete intertidal flood-ebb sampling,Cathlamet Bay, 96CB3
16 ~0900 initiate intertidal flood-ebb sampling,Cathlamet Bay, 96CB4
~2100 complete intertidal flood-ebb sampling,Cathlamet Bay, 96CB4
17 ~0930 initiate intertidal flood-ebb sampling,Cathlamet Bay, 96CB5
~2130 complete intertidal flood-ebb sampling,Cathlamet Bay, 96CB5
18 0800 begin dismantling intertidal instrumentation;benthic sampling
2000 Sproul departs for Buoy 39
2200 Sproul anchors at Buoy 39
19 0600 initiate 30-hr series 96N11
20 1200 terminate 30-hr series 96N11; depart for ArmyCorps dock
1400 tie-up Army Corps dock
Sproul-Barnes scientist meeting
1500 shopping and instrument modification/repair
1700 all personnel on 24-hr break
21 1600 onload ROV/divers and equipment
1800 all personnel due back on-board
1900 Sproul departs for EITHER North Channel or Buoy 39
22 0800 initiate neap EPA accumulation studies (e.g.,ROV or diving)
23 continue "
24 continue "
25 high resolution ETM event sampling; slack before flood, ~0300;
slack before ebb, ~1000; slack before flood, ~1500; slack
before ebb, ~2130
26 continue high resolution ETM event sampling; slack before
flood, ~0430; slack before ebb, 1100; slack before flood,
~1600; slack before ebb, ~2200
27 0600 Sproul departs for Youngs Bay
0800 Sproul anchors Youngs Bay (intertidal support) station
installation of intertidal instrumentation
28 0600 complete installation; testing
29 ~0730 initiate intertidal flood-ebb sampling,Youngs Bay, 96YB1
~1900 complete intertidal flood-ebb sampling,Youngs Bay, 96YB1
30 ~0800 initiate intertidal flood-ebb sampling,Youngs Bay, 96YB2
~2000 complete intertidal flood-ebb sampling,Youngs Bay, 96YB2
31 ~0900 initiate intertidal flood-ebb sampling,Youngs Bay, 96YB3
~2100 complete intertidal flood-ebb sampling,Youngs Bay, 96YB3
Aug 1 ~1000 initiate intertidal flood-ebb sampling,Youngs Bay, 96YB4
~2100 complete intertidal flood-ebb sampling,Youngs Bay, 96YB4
2 ~1030 initiate intertidal flood-ebb sampling,Youngs Bay, 96YB5
~2200 complete intertidal flood-ebb sampling,Youngs Bay, 96YB5
3 0800 begin dismantling intertidal instrumentation; benthic
sampling
1600 Sproul departs for Army Corps dock
1800 Sproul ties up at Army Corps dock
finale' party
4 0800 offloading
1300 Sproul departs Army Corps dock for SIO
Internet: shipsked@ucsd.edu
WWW: http://sio.ucsd.edu/