Louie,
 We're fidgiting a bit with the Sproul schedule, trying to work in another
30-hr series below the A-M bridge because we're beginning to believe that
we're not going to see any salinity above the bridge in the big river
flows we've got now and coming! Take a look and see if you see a problem;
the big difference would be the delay of the break at the ACOE dock until
the late afternoon of the 9th and morning of the 10th.  Do you see any
problems with this revision?
Si


Revised: 7/30/96, 8:46 AM

            1997-1 CRETM-LMER II Cruise Schedule

(All times are PDT)

April
 26             Sproul departs San Diego
 27             in transit
 28                 "
 29                "
 30                "

May
  1                "
  2     ?       Sproul arrives ACOE dock
                begin onloading equipment and personnel, gearing up;
                resupply and purchasing; diver installs ADCPs?
  3  0800       continue onloading equipment and personnel
                gearing up & testing
     1700       Sproul departs ACOE dock for Beaver Teminal (RM53)
     2200       Sproul arrives Beaver Teminal (RM53)
  4  0000       initiate 10-hr series 97U11
     1000       terminate 10-hr series 97U11
                Sproul departs Beaver Terminal (RM53) for North
                Channel station
     1700       Sproul anchors North Channel station (to be
                determined by earlier Barnes surveys and telemetry
                data analysis)
  5  0000       initiate 30-hr series 97S11 (N. Channel)
  6  0600       terminate 30-hr series 97S11 (N. Channel)
     0800       Sproul departs for Buoy 39
     0900       Sproul anchors Buoy 39
     1400       initiate 30-hr series 97S12 (Buoy 39)
  7  2000       terminate 30-hr series 97S12 (Buoy 39)
  8  0600       Sproul departs for downstream station, below A-M
                Bridge (to be determined by earlier Barnes surveys
                and telemetry data analysis)
     0700       Sproul anchors at new S. Channel station
     1000       initiate 30-hr series 97S13 (S. Channel)
  9  1600       terminate 30-hr series 97S13 (S. Channel)
                Sproul departs for fuel dock (?) and ACOE dock
     1730       Sproul ties up at ACOE dock
                grocery recharge, resupply & purchasing, and time off
10   0900       Sproul departs ACOE dock for North Channel station #2
     1100       Sproul anchors North Channel station #2
     1200       initiate high-resolution (flood) ETM event series
                97F11 (N. Channel)
     1700       terminate high-resolution (flood) ETM event series
                97F11
                Sproul departs North Channel for Sand Island
     1800       Sproul anchors Sand Island entrance to Baker Bay
11   0000       initiate 14-hr series 97E11, Baker Bay ebb flush
     1400       terminate 14-hr 97E11
     1700       Sproul departs for Clatsop Spit station
     1800       Sproul anchors Clatsop Spit station
12   0000       initiate 15-hr series 97D11
     1500       terminate 15-hr series 97D11
                Sproul departs for Buoy 39
     1600       Sproul anchors Buoy 39
13   0900       initiate 30-hr series 97N11 (S. Channel)
14   1500       terminate 30-hr series 97N11
                Sproul departs Buoy 39 for Beaver Terminal (RM53)
     2000       Sproul ties up Beaver Terminal (RM53)
15   0600       initiate 10-hr series 97U21
     1600       terminate 10-hr series 97U21
                Sproul departs Beaver Terminal (RM53) for ACOE dock
     2000       Sproul ties up ACOE dock
16              take-down and offload; dock social?
17       ?      Sproul departs for San Diego



Email: shipsked@ucsd.edu


Return to Ship Home Page

Return to SIO Home Page