This is a revised cruise plan for the Winant group
cruise aboard the Sproul, 4--10 November. Modifications
to the earlier plan are listed below the cruise goals.
Ed Dever
Center for Coastal Studies - 0209 phone: (619) 534-8091
Scripps Institution of Oceanography fax: (619) 534-0300
University of California, San Diego
9500 Gilman Dr.
La Jolla CA 92093-0209
Cruise Goals
This is a mooring ops and survey cruise focused on the area between
Port Hueneme and Port San Luis, CA. The plan is premised on wind speeds
less than 20 knots in the Avila Beach offshore area on 6--7 November.
If forecasts on 4--5 November suggest this may not be the case, the plan
may be inverted, beginning with mooring ops in the channel on 5 November
and ending with Avila Beach work on 9 November. The plan calls for tie up
at Port Hueneme on 10 November. Diving ops may be required in the event
of mooring failure. This cruise plan contains 2 modifications to
an earlier cruise plan posted last week.
1. We no longer go up to Morro Bay to release drifters. This
will be done by a charter vessel.
2. We tie up at Port Hueneme on the 10th and offload our group.
Ken Smith's group will then take over.
mooring and drifter release position acronyms:
AB = Avila Beach
AN = Anacapa Island
AR = Pt. Arguello
CA = Carpinteria
GO = Goleta Pt.
IN = inshore
MI = middle
OF = offshore
RO = Santa Rosa Island
SA = Pt Sal
SM = San Miguel Island
Crew List to date
Dr. Edward Dever Chief Scientist
Mr. Charles Coughran Development Engineer
Mr. Matthew Crosby Marine Technician
Mr. Paul J. Harvey Development Engineer
Ms. Erika Lawson Programmer
Mr. Grant Mills Development Engineer
Mr. Daniel Jackson Marine Technician
Mr. John Lyons Development Technician
Mr. Vincent Mikuls Sr. Electronics Technician
Ms. Tammy Koonce Resident Technician
Note: Douglas Alden and Shannon Scott (listed earlier) will probably not be
joining us. We hope to take Mr. Brett Lesh as an alternate.
04 November 0900 leave Nimitz Marfac, transit to SMOF
05 November 0800 arrive SMOF, service, prepare decks for SMIN,
CTD to SMIN (9 CTDs)*, transit to SMIN
1600 arrive SMIN, turn around
2000 prepare decks for SAOF, transit to SAOF
06 November 0600 arrive SAOF, turnaround, prepare decks for SAMI,
transit to SAMI
1100 arrive SAMI, turnaround, prepare decks for SAIN, transit
to SAIN
1600 arrive SAIN, turnaround, prepare decks for ABOF, transit
to ABOF
07 November 0600 arrive ABOF, turnaround, prepare decks for ABIN, transit
to ABIN
1100 arrive ABIN, turnaround
1500 BEGIN SURVEY: XBT/drifter from ABIN to ABOF
1830 arrive ABOF, end AB line with CTD/XBT (1 CTD, 9 XBT, 3
drifters), transit to SAOF
2100 arrive SAOF, begin ADCP section to SAIN
08 November 0000 arrive SAIN, end ADCP section, reverse and do SA
XBT/CTD/drifter survey out to SAOF
0500 arrive SAOF, end SA line (9 XBT, 9 CTD, 3 drifters),
transit to AROF
0900 arrive AROF, begin AR line with CTD, continue XBT/drifters
1230 arrive ARIN, end AR line (1 CTD, 9 XBT, 3 drifters),
transit to G line**
1300 arrive G line, begin G line with XBTs**
1630 end G line, finish with CTD (1 CTD, 9 XBT), transit to SMOF**
1900 arrive SMOF, begin CTD/XBT/drifter line to SMIN
09 November 0100 arrive SMIN, end SM line (9 CTD, 9 XBT, 3 drifters),
transit to ROIN
0330 arrive ROIN, begin XBT/drifter line to ROOF
0630 arrive ROOF, end RO line, (9 XBT, 3 drifters), transit to GOOF
0900 arrive GOOF, begin XBT/drifter line to GOIN
1200 arrive GOIN, end GO line (9 XBT, 3 drifters), transit to CAIN
1430 arrive CAIN, begin XBT line to CAOF, prepare decks for ANMI
1730 arrive CAOF, end CA line (9 XBT), transit to CA drifter line
1830 arrive CAOF drifter position, release drifter
1930 arrive CAMI, release drifter
2030 arrive CAIN, release drifter, transit to ANIN
2130 arrive ANIN, begin AN XBT line
2300 arrive ANOF, end AN XBT line (6 XBTS), END SURVEY
(except for AN CTD line), transit to ANMI
10 November 0600 arrive ANMI, turnaround ANMI, transit to ANOF
1000 arrive ANOF, begin AN CTD section
1230 arrive ANIN, end AN CTD section (6 CTDs), transit to
Port Hueneme
1400 arrive Port Hueneme, offload Winant group personnel
7 moorings (SMIN, SAOF, SAMI, SAIN, ABOF, ABIN) turned around, 1 fixed (SMOF)
21 drifters deployed
~78 XBTs
~27 CTDs
*if possible, in which case 9 November SM line would be XBTs only
(saving 3 hrs on Nov 9)
**if possible, this is an additional XBT line to further resolve what's
happening off Pt. Conception, otherwise directly to SMOF (save 3.5 hrs Nov 8)
************************
Date: Mon, 20 Oct 1997 15:33:51 -0700 (PDT)
From: Paul Harvey
Reply-To: Paul Harvey
To: Louis Zimm , Marine Facilities Shop ,
resident technicians , shipsked@ucsd.edu
Cc: Ed Dever , Betty Gunderson ,
Charles Coughran , John Lyons ,
Erika Lawson ,
Jerome Wanetick , mms-field@coast.ucsd.edu,
Paul Harvey
Subject: Cruise 16 Loading
Mime-Version: 1.0
Sproul Loading List during 31 October - 3 November for MMS Cruise #16
during 4-12 November 1997. The Sproul is due in on friday morning and
should be available for loading of computers, underway mets, and survey
gear on friday 31 October. The crane loading will take place on monday,
3 November. We will send the mooring and other gear requiring crane
loading to MarFac on monday in two loads of a 40' flat bed truck.
ITEM Size (h x w x l, feet) Wt (lbs) Total Weight
4 surface buoys 6x5x5 1600 6,400
4 anchors 3x4x4 2800 11,200
5 buoy towers 9x2x2 200 1,000
3 chain baskets 3x4x4 2800 8,400
1 rigging basket 3x4x4 2000 2,000
1 drifter basket 4x4x5 900 900
1 wire rope pallet 3x4x8 2200 2,200
2 wire rope spoolers 4x4x5 500 1,000
1 towfish 2x5x6 1000 1,000
1 towfish deck box 3x3x7 600 600
1 spool fish wire 3x3x3 300 300
1 rack w/ VMCMs 4x4x8 1200 1,200
1 seavan 8x8x20 12000 12,000
1 BT/CTD winch 3x3x3 1000 1,000
Total Weight 49,200 lbs.
Loading and Prep on friday 31 October
Install and test underway/over-the-side ADCP
Install and test underway met systems
Set up data acquisition computers and systems in dry and wet labs
(met, CTD, XBT, ADCP, general computers, micromariner,
printers, cell tel)
Loading and Prep with help from ResTech Group and MarFac Personnel on
monday 3 Nov
Load scientific gear on deck
Hang trawl block in A-frame center, towfish block in A-frame starboard,
stopper chain in A-frame port side (1/2" x 23' chain, CCS to
provide),
small sheave for 3/32" BT/CTD wire on port side
Load trash drum onto trawl winch w/ 200-500' of 9/16" 3x19 terminated
working wire
Set up BT/CTD winch w/ 440V power and test
Set up deck capstan
Provide CTD winch and set up with wire/slip rings for Neil Brown CTDs
Set up 220VAC, single phase, 50 amp power from starboard aft bulkhead to
seavan for welding power (CCS to provide wire, plug)
CCS Personnel
Install towers, Argos, and lanterns on buoys
Install top VMCMs to Buoy Argos for satellite data test
Check out VMCMs, PSensors, TLoggers, kcells
Tie down deck gear and gear in lab spaces
Please direct questions or comments to Paul Harvey 534-4540.